Web site layout - 16.2 Recovery Plan Set up a schedule linked
Wednesday, October 31st, 200716.2 Recovery Plan Set up a schedule linked to milestone completion. Plan completion dates for each mini milestone. Don’t plan on massive overtime: that hasn’t -worked so far, and it won’t work going forward. If you plan massive overtime into your schedule, developers can’t catch up by working more overtime when they get behind. Set the schedule so that if developers get behind on their miniature milestones, they can catch up by working overtime the same day. That allows them to stay on schedule on a day-by-day basis. If you stay on schedule day by day, you stay on schedule week by week and month by month, and that’s the only way it’s possible to stay on schedule for a whole project. Track schedule progress meticulously. If you don’t track progress after you set up the mini milestones, the schedule-creation process will have been just an exercise in wasting time. Check with developers daily to assess their progress against the mini milestones. Be sure that when a milestone is marked “done” it is truly, 100 percent done. Ask the developer, “If I take the source code for this module that’s ‘done’ and lock it in a vault for the rest of the project, can we ship it? Do you still have some tweaking or polishing to do, or is it 100 percent done?” If the developer says, “It’s 99 percent done,” then it’s not done, and the milestone has not been met. Do not allow developers to get off track on their mini-milestone schedules. The easiest way to get off track is to miss one milestone and then to stop keeping track. A 1-day slip turns into a 2-day slip, which turns into 3 clays, and then into a week or more. Soon there is no correspondence between the developer’s work and the milestone schedule. Once a schedule has been calibrated, do not take schedule slips lightly. If a single developer falls behind on a single milestone, expect him or her to work overtime that day to catch up. (If a developer meets a single milestone early, it’s OK to allow him or her to go home early that day.) Daily milestones must be met consistently or the schedule must be recalibrated so that they can be met consistently. Record the reasons for missed milestones. Having a record of the reasons that each milestone was missed can help to detect the underlying causes. A record might point to an individual developer’s need for training or highlight organizational dynamics that make it hard for any developers to make good on their estimates. It can help to distinguish between estimate-related problems and other schedule-related problems. Recalibrate after a short time one or two weeks. If a developer consistently misses milestones and falls more than l/2 day behind, it’s time to recalibrate that developer’s schedule. Recalibrate by increasing the current schedule by the percentage of the slip so far. If the developer has needed 7 days to do 4 days’ work, multiply the rest ofthe work by7A. Don’t play games bythinking that you’ll make up the lost time later. If you’re in project-recovery mode, that game has already been lost.
Please visit Domain Name Hosting services for high quality webhost to host and run your jsp applications.